Quick answer
Before you start a commercial build-out, confirm ten things: that the space suits your use, what the lease and work letter require, your all-in budget, who pays what, the building’s existing systems, the permit path, a schedule built backward from opening, the landlord’s building rules, a locked scope, and who will build it. Answer these before you sign the lease, while terms can still change.
A commercial build-out checklist only helps if it forces decisions early. In Seattle, most build-out problems do not start on the job site. They start earlier, with a lease signed on assumptions about cost, schedule, or building capacity that nobody checked. These ten questions are the ones to answer before a project moves from lease to construction.
This is a readiness checklist for tenants and owners, not a guide to hiring a builder. If you are comparing contractors, use our 10 questions to ask before hiring a general contractor. If the terminology is new, start with what a commercial tenant improvement is. For the services behind this checklist, see our commercial construction and tenant improvements page.
The Commercial Build-Out Checklist at a Glance
Use this table as a one-page summary, then read the detail below for each question.
1. Is the Space Right for Your Use?
A space can look perfect on a tour and still be the wrong choice for your business. Occupancy classification, zoning, parking, accessibility, and fire and life-safety requirements all depend on how the space will be used. A change of use is a common reason a project needs full plan review and code upgrades instead of a lighter permit path. Our guide to tenant improvement permits in Seattle explains how scope affects the permit route.
Ask: What was the space last used for? Does my use change the occupancy classification? Are restrooms, exits, and accessibility routes adequate for my headcount and customers? Does the lease use clause allow what I plan to do?
Red flag: The landlord or broker says code questions can wait until after signing.
2. What Do the Lease and Work Letter Actually Require?
The lease and work letter turn a construction schedule into a financial one. Five dates and terms matter most: the delivery date, the rent commencement date, any free-rent period, the deadline to use the TI allowance, and how long the landlord has to review plans and contractors. Our guide for landlords and tenants covers the work letter in more detail, and our post on how long a tenant improvement takes shows how to test these dates against a realistic build schedule.
Ask: When is the space delivered, and when does rent start? Is there a deadline to draw the allowance? Who approves drawings and contractors, and how long do they have?
Red flag: Rent starts on a date that leaves no room for design, permitting, and procurement.
3. What Is Your Realistic All-In Budget?
A broker’s per-square-foot number is a starting point, not a bid. In our Seattle office build-out cost guide, a light cosmetic refresh runs roughly $40 to $70 per square foot, a standard office tenant improvement roughly $75 to $120, and a full Class A build-out $130 to $200 or more. Those figures cover construction scope. Your total budget also needs design and permitting, furniture, fixtures, low-voltage and AV work that is often priced separately, and a contingency. We recommend 5 to 10 percent for contingency.
Ask: What is included in my number, and what is excluded? Who is budgeting furniture, IT, signage, and moving? What contingency is built in?
Red flag: A budget that is one number with no breakdown behind it.
4. Who Pays for What: Landlord or Tenant?
Most commercial leases include a tenant improvement (TI) allowance, a fixed dollar amount per square foot that the landlord contributes. Anything above it becomes the tenant’s cost. A build-out that lands 30 percent above the assumed allowance is exactly the kind of gap that surprises tenants after signing. Our post on TI allowance: what the landlord pays versus what you pay breaks down how the split usually works.
Ask: How large is the allowance? Which costs count against it? How and when is it paid out? What happens to unused funds?
Red flag: Assuming the allowance covers the whole project before a contractor has priced the space.
5. What Are the Existing Building Conditions?
Mechanical, electrical, and plumbing scope is often the largest cost driver in a build-out. In our cost guide, MEP rough-in typically accounts for 25 to 35 percent of an office tenant improvement budget. Older buildings can reveal limited electrical capacity, outdated mechanical systems, or accessibility gaps once walls are opened. A second-generation suite with usable walls, ceiling grid, and MEP already in place costs less to build out than a raw shell.
Ask: Can the electrical service carry my equipment load? Is the existing HVAC zoned for my layout? Are the sprinkler and fire alarm systems compatible with my plan?
Red flag: No one has walked the space with a contractor or engineer before the lease is signed.
A preconstruction walkthrough answers these questions with evidence. We describe the process in our overview of preconstruction services in Seattle.
6. Which Permit Path Applies, and Who Owns It?
In Seattle, commercial alterations are reviewed by the Seattle Department of Construction and Inspections (SDCI). The permit path depends on scope. Some non-structural interior work may qualify for a subject-to-field-inspection permit, while a change of use, relocating demising walls, or an initial tenant improvement for the space sends a project to plan review. SDCI also offers a blanket permit for certain office tenant improvements. Review times change, so confirm current timelines with SDCI rather than planning around a best case. Outside Seattle, Bellevue, Tacoma, and county jurisdictions each have their own process.
Ask: Which permit path does my scope qualify for? Who prepares and submits the application? Who responds to correction requests? Are secondary permits needed for mechanical, electrical, or plumbing work?
Red flag: Nobody is assigned to own the permit, so corrections sit unanswered.
7. What Does the Schedule Look Like Backward From Opening?
Construction on a straightforward Seattle tenant improvement typically takes 8 to 16 weeks, and complex builds take 3 to 6 months or longer. Design, permitting, and procurement can add as much time again. Long-lead items such as electrical gear, HVAC units, and storefront glazing can set the pace more than the crew does. Work backward from your target opening date: subtract closeout, construction, procurement, permitting, and design, then compare the result to your lease dates. Our timeline guide walks through the method step by step.
Ask: Which items are long-lead, and when must they be ordered? Can any phase overlap, such as ordering equipment while permits are in review?
Red flag: A schedule built forward from the day the lease is signed.
8. What Are the Building’s Rules for Contractors?
Multi-tenant and downtown buildings often limit work hours, elevator and loading dock access, and noisy work. Many landlords also require certificates of insurance, approved contractor lists, and sign-off on drawings before work starts. These rules affect sequencing, labor cost, and schedule, and they are easy to overlook when you are focused on the floor plan.
Ask: Can the landlord provide building rules and contractor requirements in writing? Are there restrictions on after-hours work, freight elevator scheduling, or utility shutdowns? Are there noise-sensitive neighbors?
Red flag: Requirements surface only after you have chosen a builder and priced the work.
If your space is in an occupied building, our commercial team plans around these constraints from the start. See our commercial construction page for how we approach occupied-building work.
9. Is the Scope Locked, and Who Approves Changes?
Scope changes after pricing are among the most avoidable causes of lost time and money. Before drawings are submitted, settle layout, finishes, equipment, signage, and technology needs. Decide who has authority to approve changes, and agree on a written change process so every adjustment has a documented cost and schedule impact before work proceeds. Combining design and construction can reduce handoffs, which we explain in our post on design-build for Seattle office build-outs.
Ask: Who signs off on changes on our side? How are hidden conditions handled? What is the cutoff for finish selections?
Red flag: Several people can change the design, and nobody tracks the cost.
10. Who Will Build It, and When Should They Join?
The best time to involve a contractor is before you sign the lease. A site walkthrough, preconstruction budget, and schedule review can reveal hidden mechanical problems, test the allowance, and give you leverage while terms are still negotiable. Vetting a builder is its own process, covered in our general contractor selection checklist. Envision Builders Inc. uses a managing general contractor approach that brings schedule planning, subcontractor coordination, and risk review into the project early. If that model is new to you, read what a managing general contractor is.
Ask: Will the contractor walk the space and review the lease before I sign? Who prices the scope, and how are subcontractor bids leveled? Who manages the project day to day?
Red flag: Hiring a builder only after the lease is signed and the dates are fixed.
Does the Checklist Change for Restaurants, Medical Offices, or Fitness Centers?
Yes. The ten questions still apply, but some uses add scope that moves cost and schedule. Restaurants, medical offices, and fitness centers generally take longer than offices because of added plumbing, ventilation, and code requirements. Restaurant kitchens add hood systems, grease interceptors, and health department review. Ask each question with your specific use in mind, and plan extra time for long-lead kitchen or specialty equipment. Our post on fitness center and restaurant build-outs in the Puget Sound region covers how these projects differ from offices.
Key takeaways
Answer these ten questions before you sign the lease, not after. Per-square-foot figures are a starting point, and a contingency of 5 to 10 percent belongs in the budget. A TI allowance rarely covers everything, so price the space first. Existing electrical and HVAC capacity often drives cost more than finishes. Work the schedule backward from your opening or rent start date. Bring a contractor in early for a walkthrough, budget, and schedule review.
Frequently Asked Questions About Commercial Build-Outs
What should be on a commercial build-out checklist?
A strong checklist covers use and code fit, lease and work letter terms, total budget, allowance and who pays what, existing building systems, the permit path, a backward schedule, landlord building rules, locked scope with a change process, and when to bring in a contractor. Each item should be answered before you sign the lease.
When should I start planning a commercial build-out?
Start before you sign the lease. Design, permitting, and long-lead procurement can take as long as construction itself, and a walkthrough with a contractor before signing can reveal cost and schedule risks while lease terms are still negotiable.
What is the difference between a build-out and a tenant improvement?
They are closely related terms. A tenant improvement usually describes build-out work tied to a new lease, often with a landlord allowance. A build-out is the broader term for converting a space for a specific business use. Cost drivers such as MEP scope, permitting, and finish level are largely the same.
Who pays for a commercial build-out, the landlord or the tenant?
It depends on the lease. Many leases include a TI allowance, a fixed amount per square foot from the landlord, and the tenant pays costs above it. Confirm which costs the allowance covers, when it is paid, and whether it expires before you sign.
How much should I budget beyond construction costs?
Plan for design and permitting, furniture, fixtures, low-voltage and AV work, and a contingency. In our Seattle office cost guide, design and permitting typically run 8 to 12 percent of the total budget, and we recommend a contingency of 5 to 10 percent.
Do I need a permit for a commercial build-out in Seattle?
Commercial alterations in Seattle are generally reviewed by SDCI, and the permit path depends on scope. Some non-structural interior work may qualify for a lighter path, while a change of use or an initial tenant improvement typically needs plan review. Confirm your path with SDCI or your architect.
Should I hire a contractor before signing the lease?
Yes, if possible. A contractor can walk the space, review the lease and work letter, and build a preconstruction budget and schedule. That gives you leverage to negotiate the allowance and rent start date, or to walk away from a space with hidden problems.
Sources and Further Reading
SDCI STFI checklist for multifamily and commercial buildings
SDCI Tip 100: Getting a Multifamily or Commercial Construction Permit
Envision Builders: commercial construction and tenant improvements
Planning a Commercial Build-Out in Seattle?
Talk to our team before you sign. Envision Builders Inc. will walk your space, review your lease dates and scope, and help you build a realistic budget and schedule across Seattle, Bellevue, Tacoma, and the greater Puget Sound region. Talk to Our Team | Call (425) 757-4591 | Info@envision-builds.com
Explore our commercial construction and tenant improvement services or browse our project portfolio, including the Stillpoint Yoga Studio tenant improvement.
About the author: Tim Kairez is Project Executive and Owner of Envision Builders Inc., specializing in multifamily, mixed-use, and commercial construction throughout the Greater Seattle region.